Öresund Bridge
Project status
Completed

Öresund Bridge 25 years
Since 2000, the Öresund Bridge connects Sweden and Denmark. But it connects much more than that. The bridge also enables access to work, studies and culture. On July 1, 2020, the 15.9 kilometer bridge celebrates its 20th anniversary.
Client:
Sundlink Contractors
Service:
Construction Management
Market segment:
Bridges, Railways
Start date:
Completion date:
City:
Malmö
State:
Skåne County
Country:
Sweden
51
caissons (bridge bases) were cast. The height varied between 12 and 20 meters. The heaviest weighed 4,700 tons, the lightest 2,500 tons.
240,000
cubic meters of dredged masses were used as filling in Norra Hamnen and for building Peberholm.
320,000
tons of concrete were used, corresponding to 128 Olympic-size swimming pools.
203.5
meters are the pylons on the high-level bridge – Sweden’s highest structure.
20,000
tons is what the pylon caissons weighed.
25
kilometers of cable was used for the high-level bridge. 80 pairs of cables were installed and each individual cable has a breaking strength of 2,000 tons.