Press release (regulatory)
Skanska has signed a contract with Nordex Sverige AB to build a new wind farm in Viksjö outside Sundsvall, Sweden. The contract is worth about SEK 360 M, which will be included in the order bookings for Sweden for the first quarter 2020.
The project at Björnlandshöjden includes roads, crane plans and foundations for 41 wind turbines.
Construction start is scheduled for March 2020 and the project will be completed in August 2022.
Skanska is one of the leading development- and construction companies in the Nordics, with operations in building construction and civil engineering in Sweden, Norway and Finland, and developing residential- and commercial property projects in select home markets. The commercial development stream is also active in Denmark. Skanska had sales of about SEK 70 billion and more than 15,200 employees in its Nordic operations during 2019.
For further information please contact:
Andreas Joons, Press Officer, Skanska AB, tel +46 (0)10 449 04 94
Direct line for media, tel +46 (0)10 448 88 99
This and previous releases can also be found atwww.skanska.com.
Are you a journalist looking for information about Skanska or have questions about our operations? Our Media Relations team can help with press inquiries, interviews, background information and access to relevant resources.

Jacob Birkeland
Head of Media Relations & Public Affairs

Andreas Joons
Media Relations Manager

Olof Rundgren
Media Relations Manager